ALL of them requiring water, affecting water or being affected by water in one way or another.
Grays Harbor, Lewis, Mason and Thurston Counties approved the watershed plan on May 28th but there is still plenty of related work for the Partnership including:
| Remember, Chehalis Basin Partnership meetings are scheduled for:
June 25, at the Lucky Eagle Casino from 9:00 a.m. to 11:30 a.m. July 23, location to be determined August 27, location to be determined September 24, location to be determined October 22, location to be determined November 19, location to be determined December 17, location to be determined |
DATE: Friday June 25, 2004
TIME: 9:00 A.M.o 11:30 A
| General Partnership Business | 9:00 a.m.- | - |
| Welcome, introduce members and new visitors | (5) | Chair |
| Identify special issues of concern and adjust agenda(5) | Members/Chair | - |
| Committee Reports | - | - |
| Citizens' Advisory Committee | (5) | To be Announced |
| Steering/Technical Committee | (10) | Mark Swartout |
| Water Quality Committee | (10) | Terry Willis |
| Other Business | - | - |
| Review Annual Work Plan and unfinished Tasks | (5)
- |
Kahle Jennings |
| Future Meeting Locations and Logi stics | - | - |
| ACTIONS TO BE TAKEN AT THIS MEETING: | - | - |
| Decisions on unfinished Work Plan tasks | - | - |
| Decisions on meeting locations | - | - |
| Special Project Status Reports, Budget Updates and Committee Reports. | - | 9:40 a.m |
| Watershed Plan (RCW 90.82) | (60) | CBP and Steering/Tech Comm. |
| a) Reflections on the Planning process and results | - | - |
| b) Begin Discussion of Implementation | - | - |
| What the Chehalis Plan says regarding implementation | - | - |
| What the law requires regarding implementation | - | - |
| What are the concerns of Partnership members regarding implementation | - | - |
| Who is implementing plan recommendations already | - | - |
| Salmon Recovery Project (RCW 77.85) | (20) | Lee Napier |
| ACTIONS TO BE TAKEN AT THIS MEETING: | - | - |
| Possible Direction on how to proceed with implementation | - | - |
| Special Presentation | - | 11:00 a.m. |
| None Scheduled | (0) | - |
| Open Comment | 11:00 a.m. | - |
| Any remaining issues identified in agenda item A2 | (30) | Audience |
| Chair Adjourns Meeting | 11:30 a.m. | - |
Attachments included with this mailing:
March 26 th Chehalis Basin Partnership meeting summary and attachment
April 9 th special CBP meeting summary and attachment
Information sheet on watershed planning implementation (Phase 4 of RCW 90.82)
This page created and maintained by Chehalis River Council